Trammell Crow Company is the developer behind the Balfour/Fitzgerald Senior Living Project at the old Safeway site. Gilbane Building Company will be building it.
Below are updates and information about the project, including the latest monthly update and traffic and control plans for the utility work that commenced February 5. The work hours are 9:30am to 3:30pm Monday–Friday. The work will begin on 48th Place and work counterclockwise to MacArthur Blvd, U Street, and then V Street. Estimated days of work for each section are noted below.
- 48th Place — 17 Days
- MacArthur Blvd — 29 Days
- U Street — 23 Days
- V Street — 8 Days
Gilbane’s monthly update (March)
Wet utilities road work duration
Approved traffic and control plans
Truck and parking restrictions
BZA Statement, including the Memorandum of Agreement and the Construction Management Agreement